Progress

DATE TARGET ACTIVITY RESPONSIBLE PERSONS PENDING(YES/NO)
14/06/2014 to 21/06/2014 Week 1 Writing the Requirements document and Planning the application Start of the design document and interface sketching Alice Nabawanda, Napoleon Katambira, and Christine Kabajwisa, NO
Week 2 Working on the mainActivity class containing the splash scree.Working on the second activity that has two buttons to enable different users navigate into the application

This included enabling a farmer capture a picture of his/her crops and be able to post it and the information on the product and farmer as well as the customer being able to view the posted produce.

Alice Nabawanda, Brain Muhimbura ,Napoleon Katambira, Christine Kabajwisa and Ivan Peter Mbwabwa No
Week 3 Creating all interfaces and creating tables for the database using php and sql and working on the implementation document . Alice Nabawanda, Brain Muhimbura, and Ivan Peter Mbwabwa No
Week 4 Connecting all interfaces and creating a database connection between the app and a server: using php and sql in order to store the data on a network or server to enable sharing of data. Brain Muhimbura, Napoleon Katambira and Ivan Peter Mbwabwa NoDatabases pending
Week 5 Finalising with the implementation document and updating the requirements document in accordance to the new changes in the requirements and finalising with the blog.Finalizing the databases Alice Nabawanda,, Brain Muhimbura, Napoleon Katambira, Christine Kabajwisa and Ivan Peter Mbwabwa No